DNI Package-1
Project Summary:
·
Bulk Distribution System Improvements
·
Service Reservoirs
·
Distribution Network Improvement
·
Rehabilitation of Existing:
Ø Surface
Water Sources
Ø Transmission
Mains
Ø Water
Treatment Plants
Ø Service Reservoirs
The Distribution Network Improvement For Efficient NRW Management- Package -1 lies within the Kathmandu Valley, which is intended with new network of water supply system within different wards of Kathmandu and Lalitpur Municipality. Our project has three site namely DNI-1, DNI-2, DNI-6 where DNI-1 is surrounded by Bisnumati River on the west and South, DNI-2 includes Dhobi Khola and Bagmati River on the East and DNI-6 has Jawalakhel on the North-West and Patan Industrial Estate on the South-East along with the Ring Road on the South-East and South- West. The Current piped water supply demand in Kathmandu Valley, including unaccounted for water, is estimated to be over 320 million liters per day (MLD). However, the combined production capacity of the groundwater and surface water sources in the dry season is reported to be about 100 MLD and even in the wet season, the production capacity is reported only to reach 150 MLD.
Under these water shortage conditions, KUKL has applied a rationing system whereby water is allowed to flow to different section of the Metropolitan/urban area in rotation. As most areas receive intermittent supply with low pressure, use of pumps to suck water and bypassing of water meters are believed to be quite common techniques used by consumers. Water quality at the consumer’s end is far less than desired and it is a common practice to treat or boil water before drinking or cooking.
Since
this Project is being introduced to upgrade existing water supply system within
Kathmandu Valley and ultimately by integration into Melamchi water,
better quality of everyday life of city dwellers is expected.
The project has been divided into three locations DNI-1, DNI-2 and DNI-6 respectively. Water supply reticulation over the project site is designed to enhance by adding up 1000mm, 900 mm, 800mm, 700mm, 600mm, 500mm and 400mm dia. Primary Main (DI pipe) as supply mains, 300mm, 250mm, 200mm and 150mm dia. Secondary Main (DI pipe) and 110mm, 90mm and 75mm dia. Tertiary Main (HDPE pipe) of total of 302 km approximately.
DNI-1 |
DNI-2 |
DNI-6 |
Main Constrain:
- Road Cutting Permission from concern authorities ( DOR, Corridor, KMC)
- Change in design ( Pipe network, addition of Valve, division of small DMA)
- Earthquake 2072
- Third Party damages
- Procurement of valves and appurtenances
- Local issues in Kapan Area
- Delay in arrival of Melamchi water for Commissioning, flushing and disinfection work.
- Lack of coordination from KUKL